36 Dwellings, Bow Road, London

The site in the shadow of the Olympic Village was subject to significant demolition and site clearance along with sewer and service diversions.

The site was built in 3 blocks and occupied the full site area on a TFL red route meaning site logistics were key and challenging.

The concrete frame was clad in brickwork with composite triple glazed windows as acoustic considerations were a significant factor.

The units were a fitted out to an excellent private sale specification with the affordable element taken by Gateway Housing.

Key details

Building size

35,370 sq/ft

Project duration

66 Weeks

Client

Aitch Group

Contract type

JCT Design and Build

Architect

Stock Woolstencroft

Structural Engineer